Guides for homeowners: How an extension is built: the stages in order

A clear idea of the order of work helps you plan your life around the build, and know what you are paying for at each stage.

Extension footings and first courses of blockwork

Every extension is different, but most follow the same order. Knowing it helps you make decisions at the right time, because changes are cheap on paper and expensive once the walls are up. Timings depend on the size of the job, the weather and the supply of materials, so we have not put dates on the stages. Alistair gives you a realistic timeline with your quote.

Before work starts

Drawings are prepared, and planning permission is applied for if it is needed. Building control gets the plans, and if the extension is near a shared boundary you may need to serve notices under the Party Wall Act. If the extension opens into the house, the structural engineer's calculations are also done at this stage. Fixed choices, such as the position of the kitchen and doors, are best settled now.

Groundworks and foundations

The area is cleared and the footings are dug. Drains running through the area may need to be protected or diverted. Building control inspects the trench before concrete goes in, and again as the work rises through the floor level. This is why the work must be left open for inspection.

Walls and roof

The walls are built up to roof level, with insulation in the cavity, and the roof structure goes on, followed by the roof covering, windows and external doors. At this point the extension is weathertight, and work inside can carry on whatever the weather.

Opening up the house

Once the extension is weathertight, the existing wall between it and the house is opened. If it is load-bearing, temporary supports go in and the steel beam is fitted. See what is involved in a knock-through for how this works. Leaving this step until the extension is watertight keeps dust and weather out of the house.

Fitting out

The electrics and plumbing are roughed in, the walls and ceilings are insulated and plastered, and the heating goes in, including underfloor heating if you are having it. Then the second fix follows: sockets, switches, lighting, radiators and bathroom fittings.

Finishing and sign-off

The kitchen or bathroom is fitted, the floors go down and the decorating is done. Building control makes a final inspection, and when it is passed you receive a completion certificate. Keep it with your house papers, because a buyer's solicitor will ask for it. See our extensions page for examples.

What can change the order

The sequence above is typical, but real jobs shift around it:

  • What the ground reveals. Unexpected ground conditions or drains can change the foundations.
  • Inspections. Work has to wait for building control to inspect before it is covered up.
  • Deliveries. Windows, bi-fold doors and kitchens can have long lead times, so they are best ordered early.
  • Weather. Groundworks and the shell are the most exposed to it.
  • Changes of mind. A change after the walls are up is much more disruptive than one on paper.

Questions to ask your builder

  • What is the order of work, and when do I need to have made each decision?
  • When will the kitchen, windows and doors need to be ordered?
  • When will the house be opened up, and what will that mean for daily life?
  • How will changes be agreed and priced?
  • Who will inspect the work, and when do I get the completion certificate?

For how to cope with the disruption, see preparing your home for building work.