The Party Wall etc. Act 1996 is a separate piece of law from planning and building regulations. It is about your relationship with the neighbours when building work affects a wall or ground you share. It is the homeowner's responsibility, not the builder's, so it is worth knowing about before work is planned.
What the Act is
The Act gives you the right to carry out certain kinds of work near or on a shared boundary, as long as you follow a process: you tell your neighbour in writing, and they can agree or dispute. It also protects the neighbour, who can have the work checked by a surveyor. It applies in England and Wales.
When it applies
Typical triggers for an extension include:
- building a new wall on or right up to the boundary between your property and your neighbour's;
- work to a shared wall, such as cutting into it to fit a steel beam, or raising it;
- digging foundations close to a neighbouring building and deeper than its foundations. The Act sets distances, so check the current guidance for your case.
Not every extension is affected. One built well inside your own land, away from the boundary, may not need a notice.
Serving notice
If the Act applies, you serve a written notice on each affected neighbour before the work begins, normally one to two months ahead depending on the type of work. The notice sets out what you plan to do. The neighbour can then:
- consent in writing, and work goes ahead; or
- dissent, which leads to a party wall award.
If your neighbour does not agree
A neighbour who dissents does not have the power to stop your extension. Instead, a surveyor, either one agreed by both of you or one each, produces a party wall award that sets out how and when the work can be done and records the condition of the neighbouring property before it starts. As the building owner you normally pay the reasonable costs of the surveyors. This is another reason to talk to your neighbour early.
Next steps
The government publishes a guide to the Party Wall etc. Act, including sample notices. If you are unsure whether it applies, ask when Alistair visits to quote, and take advice before you serve anything. Read next: planning permission or building regulations, and our extensions page.
Common questions
Who pays for the surveyors?
As the building owner, you normally pay the reasonable costs of the surveyors involved, including your neighbour's if they appoint one. Using one agreed surveyor for both sides can keep the cost down.
What if I do not serve a notice?
You are putting the project at risk. A neighbour who was not given proper notice can take action, which can halt the work and add cost. It is much cheaper to do it properly at the start.
Does the Act replace planning permission or building regulations?
No. It is a separate process between you and your neighbour. See planning permission or building regulations for how the approvals differ.
Who do I serve the notice on?
On the owner of the neighbouring property. If it is rented, the owner is the landlord, and it is good practice to let the occupiers know too.
Tips for keeping things friendly
- Talk first. A conversation before the formal notice makes everything easier.
- Record the condition of the neighbouring wall and rooms near the work before it starts. A surveyor does this formally as part of an award.
- Give notice in good time, because the notice periods have to run before work begins.
- Keep the neighbour informed about start dates, noise and access.